TIMING
• Map 1: Sidewalk works from May 21, 2024, for two (2)
weeks, approximately. June 4 for one (1) day.
• Map 2: Road works a one (1) day operation on June 1,
2024, approximately.
• Map 3: Detour during one (1) day operation June 1, 2024,
approximately.
• Dates are tentative and may change.
• Work hours: 7:00 a.m. to 5:00 p.m., approximately.
• There may be overnight and/or weekend work, if
required.
IMPACT
• Rolling temporary lane closures.
• Periodic sidewalk and crosswalk closures.
• Temporary relocation of TTC bus stops, if needed
• There will be a Paid Duty Officer, flaggers to direct traffic, as
needed.
• Minor field modifications may occur when needed
to complete work safely and minimize impact on
the public.
LOCATION
• Norfinch Drive, Oakdale Road, York Gate Boulevard on
Finch Avenue West.
WORK DESCRIPTION
• Roadway grading, sidewalk and road works.
Detailed Description
As part of the Finch West Light Rail Transit (LRT) Project, crews will be doing roadway grading, sidewalk and road
works at Norfinch Drive, Oakdale Road, York Gate Boulevard on Finch Avenue West.
The work is scheduled to start on May 21, 2024, and will last till June 7, 2024, approximately.
Work may be rescheduled due to weather conditions or unforeseen circumstances.
Please take extra care when navigating near work sites, and always make eye contact with the driver before
crossing in front of any equipment or vehicle.
There will be a Paid Duty Officer, flaggers, and detour signs to direct traffic, as needed.
Minor field modifications may occur when needed to complete work safely and minimize impact on the public.
Noise and vibration will be monitored when required during these activities.
WORK HOURS:
• Work will primarily occur Monday to Friday from 7 a.m. to 5 p.m. There will be overnight and/or weekend work
7 p.m. to 6 a.m., if required.
• Signs are installed to keep residents informed about the closure.
• Dates are tentative and may change. Please visit us at www.metrolinx.com/finchwestlrt for up-to-date information.
• Inclement weather or unforeseen circumstances may delay work activities.
WHAT TO EXPECT:
• Heavy trucks and equipment in the area.
• Due to the nature of the work, at times there will be dust, noise and vibration associated with this work.
• Nearby businesses and residents can expect noise from excavators, bobcats, vacuum trucks, and other construction equipment
caused by road work activities.
• Expect delays near work zones.
• A minimum of one lane of traffic in each direction along Finch Avenue West will be always maintained.
• There will be a Paid Duty Officer, flaggers, and detour signs to direct traffic, as needed.
PEDESTRIAN, TRAFFIC AND TRANSIT DETAILS:
• Road and sidewalk restrictions are in place within the construction area to protect workers and the public.
• Please take extra care when walking near work sites, and always make eye contact with the driver before crossing in front of
any equipment or vehicle.
• Pedestrians will be re-routed around the construction area when possible. For safety reasons, pedestrians may be diverted to
the sidewalk on the opposite side.
• TTC bus stops will be closed or relocated away from work zones, as needed.
• Relocation of bus stops is done in consultation with TTC.
• Access to TTC will be always maintained, please visit www.ttc.ca for more information.
2024-06-03 FWLRT Construction Notice – Update Temporary Traffic Changes Norfinch FAW (1)