Traffic plan for road works SW of Milvan Dr (Oct. 19 to Nov. 3rd)

Traffic plan for road works SW of Milvan Dr (Oct. 19 to Nov. 3rd)

Mosaic will close access to both existing driveways and pave a replacement entry point at the SW corner of Finch W & Milvan Dr. . The other driveway on Milvan Dr. will remain open. Hence,  two points of access will always be maintained to the strip shops area.  This arrangement will promote road and vehicular safety while expediting the road works expected to be completed within two weeks of the Oct. 19 start date. The road works will include City ROW (bike lanes, sidewalks, curbs) that will be accessible to the public and the retail patrons.